New Build, Maidenhead

This detached new build in Twynham Road, Maidenhead was built by Thermohouse ICF. This is a 1 storey detached home with a ground floor / first floor area of 320 sq metres and a habitable loft house.

Thermohouse Support

Thermohouse UK used a team of experts and specialised installers for this rapid build project.

Thermohouse technical team were available throughout the process to offer any guidance that was required, ensuring a streamlined building process.

Thermohouse built a highly efficient thermal house shell in 12 weeks.

210 sqm of external walls were built using Thermowall 350 mm external blocks.

110 sqm of internal load bearing walls were built using Thermowall internal 250mm blocks

270 sqm of our Thermoroof panels were used acting as the slopped roof.

In Build and Completed Photos